September 25, 2013

Hauled 2 loads of 57 stone to job for back-fill around storm box (box culvert) took old skimmer off of old existing storm box to build new skimmer for storm box 100. Box culvert weir. Took to yard for skinny bob to cut to size. Picked up hammer drill to mount brass disc in storm boxes at twin oaks. 3 boxes.


Contractor continued pond excavation and slopes. We continued hauling material to perimeter of pond and grading. Removed old skimmer from demo control structure so we can fabricate one for #s-100. 54 loads/972 CY.

Met with Toho locator to determine valve and feeder main for 6" BFP to be relocated. Told Butch, John and Larry what we found and how we could move it. Told Larry the fittings we would need and to forward everything to John at his office. Sent photo to Beau of top soil we accumulated from pond excavation to see if he had a use for it somewhere because we will have extra.

Problems: need truck for debris. Need #s-100 skimmer, #s-108 skimmer and grate.