September 24, 2013

Started pump at 5:30 to have box pumped down by 7:30 when concrete saw men got there to saw box. Men got there and had a hard time sawing box so we had to dig out more for them raising box to get sloppy and wetter. Rain did not help, so we are going to have to put some 57 stone in sloppy wet areas to get compaction. Need rock so i went to yard and check out dump truck to go get rock in the morning. No driver.


Carl's concrete cut approximately 4" off top wall for clearance of top slab to finish pavement. Continued cleaning unsuitable fill and stacking debris. Continued filling and grading pathway around top of pond. Shot pond elevations for excavation contractor. Pond contractor continued working on slopes. No trucks again today.

Met with Larry, John and Butch about driveway at structure #s-100. They discussed several options and decided to use my idea and maybe change from base and asphalt to concrete at approach. Told Larry we need the skimmer and missing grate. Also to check with Hanson about casting four sections of invert for #s-100 since box culvert is flowing full.

Problems: need truck to haul away debris and demo materials.