September 26, 2013

Went to Twin Oaks to put survey disc on control structures (3). Went to CC Pond and met with City to get approval on invert design for forming inverts on land and setting them in box. Went and got material for forming and steel from yard. Made 2 sets of forming 2 move to go and need to set steel tomorrow. Went to shop and made chain and angle iron to go in concrete for lifting.


Subcontractor continued pond excavation but dump site is still too wet for import. Continued filling and grading around perimeter of pond. Began restoring grades for finishing slopes. Built two forms for inverts in #s-100 and pre-fabbed material for the remaining two. 

Talked to Beau about setting up pump for pond contractor. I also talked to him about hauling top soil pile to yard on MLK to screen later. Gave Larry the list of materials we will need to move 6" BFP. Toho water located gate valve for BFP and raised to grade. Dub Kelley well and helped set up pump for contractor. Used three loader buckets of rock and told him if he needs anymore they would have to buy it. We need what we have for structure #s-100.