September 13, 2013

Continued top of pond grading, removed remaining 36" RCP from existing box culvert and marked for saw cut monday. Continued pond excavation.

contacted century link about cable conflict at box culvert. They cut and moved cable from excavation until we have completed our work. Met with sub-contractor about pouring collars for new box culverts but he is too busy. I have contacted two others but none have committed or given a price yet. Pond contractor did not return my phone calls or come to jobsite as he said yesterday. Called Larry to inform him that we will have to inform him that we will have to core and install a roof drain and underdrain in new box culvert since we found these in the existing during excavation.

Problems: exposed a fibre optic cable in conflict with #s-100. Different cable from yesterday.