Cleaned up trash and roots boards trash pipe from around lift station area. Back fill catch basin. We set tuesday and set grate on top of box. Start to dig up 48" pipe and lay another joint closer to box culvert but ran into a fiber cable. No one would take ownership of line so we cut it to see who if any one would come and complain. Lost 4.5 hours due to locates and cable.
Installed 6" orifice pipe in control structure #108. Continued hauling clearing debris from site and began loading and hauling trees to sawmill. Continued stripping, balancing and grading for pathway around pond top.
Problems: began opening area at box culvert location but found an unmarked directional bore in direct conflict with structure.
Called pond contractor to discuss the excavation process. His operator said he was not finished the south end of pond. I talked to Paul Walsh about it and he stated that they had completed all they could without layout. I told him the layout was in place when he started and they didn't protect it. I called Beau and told him about the situation and he said they had an agreement about the pond excavation along with a letter generated that addressed it. He said to meet with Paul and try to resolve it. We uncovered an unmarked directional bore under the existing box culvert at structure #100 location. Called Larry and all locate services to determine what it was but no one claims it. It will have to be moved prior to installation.