Went to Deland to get measurements on box culvert box and box culvert pieces. Came all the way back to turn pipe and then had to turn around and go back to Sanford to pick up gaskets for 48" ADS pipe and then back to st. Cloud to get PVC fittings for bleeder pipe for control structure.
Continued hauling clearing debris to be burned. Hauled two remaining manhole bases to Kissimmee yard. Continued surface grading of pond top and moved materials out of pond excavation area. Began clean raking of tree area in pond. Mudded 15" HDOE at storm structure #107. Continued pond excavation. 113 loads/ 2034 CY.
Met with Larry about structure #100 at box culvert. He brought more shop drawings this morning that clarified the connection but was too late to reschedule cutting for today. Talked to Beau about us picking up on
site for dimensions and elevations needed to avoid any conflicts. Re- scheduled crane and delivery of structure and box culvert for monday.
Problems: concrete sawing had to be re-scheduled for monday due to information regarding new structure.