July 23, 2013

Used saw and air hammer to break through seawall. Put joint of pipe through wall and secured. Saw cut and removed asphalt base and valley butter for open cut of lakeshore drive. Hit existing 15" RCP sanitary sewer that was not located. Called inspector and safed up.

Beau called and asked for Scott to work at twin oaks. Hydraulic saw and hydraulic hammer never arrived so we had to use a hand saw and rent an air hammer. This caused us to take 8 hours to cut through wall before we could lay pipe. While excavating to install one more pipe, we hit a 15" RCP sewer main that was not located. It also is in conflict with storm pipe as we can't go over or under. City inspector was onsite and is aware of conflict. Did a makeshift repair for tonight and i also notified Beau.

Problems: hydraulic saw would not work and hydraulic hammer did not arrive.


Saw cut road and talk up asphalt and base. Mark wall and saw cut and break out. Base 1 1/2' thick. Set first joint and dug out for second and hit 15" VCP sewer. Safe up and will come back in the morning and fix. Locater did not mark and also not in straight line between m.h.