Toho water authority replaced 15" VCP sewer main. We excavated for them to speed up the process. Laid 29" x45" ___ from seawall to sidewalk across road. Back filled to top of pipe and compacted. Stopped at sidewalk because seawall sidewalk has to be replaced before opposite side is removed.
city inspector informed toho waster authority that sewer main had no locates. Took 3 hours so it affected what we needed to accomplish today. Jimmy talked to Beau about progress and sent photos of repair and over pipe run. Called to have bobcat and roller brought to job in the morning. Also picked up brick and ___ for mud work tomorrow.
Problems: rained twice so we couldn't mud pipe to seawall or place any more backfill.
Toho water department fixed broken sewer main with us digging it out and using 2 yards of 57 stone. Took back air compressor and jack hammer to Neff. Rain rain and more rain. Still got across road and ready to back fill and put down limerock and asphalt by Friday.
Problems: 4 hours delay in project no locate.