Put out all required MOT for open cut and closed road. Excavated behind seawall and located tiebacks. Excavated to grade marked location of pipe on wall and put down rock bedding. Removed necessary sidewalk, laid out cuts on asphalt and began cutting roadway put down wellpoint system for sanitary sewer.
Beau stopped by to check progress. I told him what we had exposed and that there was no extension footer on back side of wall. I also told him mini excavator would not be delivered until late afternoon so i would use track hoe. He said would be going down south tomorrow, but if we needed any thing to call.
Problems: didn't get turbidity barrier in time to put out today.
Close road. Reroute traffic. Used J.T. Hoe to locate utilities of wall tie? Backs. Went to yard to get power unit for concrete sand. Beau showed what was wrong with unit and I worked on it till it caught fire in my truck, so I took it to shop and gave to Skinny Bob. Well point men put 90% of system in and fain came at 4:30 so they quit and will return tomorrow.