August 6, 2013

Set up and laid 100' of 24" sanitary sewer from MH #2 to MH #1. Backfilled and compacted two lifts with marking tape. Set risers on MH#2 and MH#3. Density tests were not taken today because excavated material is not working. Lab technician took two material samples for new proctors. MOT for lane closure was delivered along with two loads of #57 stone.

called Beau to discuss air testing process for sanitary sewer and what Toho is requiring. We have two 24" plugs that should work but if not Beau said to rent them. It has been very hot in the past two days and is even hotter in the 14' ditch. We havce to watch the pipe layers and make sure they get breaks in the shade and stay hydrated.


Set up and start running pipe toward existing MH. Ran 1/2 way and start to back filling and compacting. Density man came and fill too wet. Took more dirt samples to get another proctor to see if it would help.


Picked up mower and herbicide. Mowed civic center pond.