Set up and laid 24" sanitary sewer from MH #3 to MH #2. Set MH #2, backfilled and compacted 6 12" lifts. Two lifts did not pass due to high moisture level in backfill material which contains a large amount of clay's.
Beau stopped for about ten minutes to check progress. Met with concrete contractor to price valley gutter and sidewalk for Wednesday. Confirmed layout for work tomorrow. Also contacted sunbelt and ordered MOT needed for concrete pour to be delivered tomorrow. Ordered two loads of #57 stone for tomorrow and scheduled testing of sewer main with Toho water.
Ran pipe from MH #3 to MH #2. Set MH #2 and continued with backfill. Density man came and only 1 lift around MH #2 passed. Too much moisture in fill. Clay is holding water. Tomorrow we will start to lay toward existing MH and rest of crew will cut some fill out and mix it and repack. ??? Hopefully it will pass. I think we have got to pack it longer.