August 2, 2013

Completed 24" sanitary sewer to manhole #3 and set structured backfilled and compacted lifts to grade. Density tests taken on backfill and passed.

called for MOT so lane closure to pour concrete next week. Called dirt contractor to tell him time frame for pond excavation to begin. Ordered two loads of #57 stone for completing pipe work. Called concrete contractor to confirm pour next week. Called surveyor to confirm layout for concrete pour monday.


Finished laying to MH #3 and set bottom back fill and get compaction 15' cut to bottom of rock for MH. What happened to 9' cut? Bring up to grade between MHs safe up for weekend. Job drying out finally! Back fill compaction all test ok.