Take out control box and 8 joints of 36" RCP. Replaced with 48 ADS and flared end section. 40'. wet.
Removed control structure from existing pond and 80' of 36" RCP. Set 48" MES and laid 48" HDPE across access road. Mudded pipe to MES. Back-filled and compacted across rd. Loaded 20 yard dumpster with concrete debris and hauled to Kissimmee yard for crushing. Contractor formed and poured 35' of 6' valley gutter/approach and 15' of sidewalk at seawall.
met with Paul Walsh to look at pond layout and go over existing utility locations. Called Larry to confirm locate updates. Talked to Beau about any agreement he has with Paul Walsh concerning the pond excavation. Also discussed the dewatering problems with the pond. He said to rent a pump from Thompson for dewatering and that Paul Walsh would be maintaining it.