August 29, 2013

Ok. Pond pump and grease and fuel her. Finish laying 18" ADS (11') into catch basin mudin and clean up area. Back-fill all pipes and safe up.


Completed pumping existing pond for use as impoundment for new pond excavation. Began stripping large cypress trees to be removed for new pond. Removed all dirt weirs put in for pipe work and finish graded the areas as necessary. Marked the ends of all pipe that extend into new pond limits. Layout of pond was freshened up.

Paul Walsh is to be here tomorrow about starting pond excavation Tuesday. Concrete to complete valley gutter and sidewalk was cancelled again and was rescheduled for tomorrow at noon.