Dug up 2 MH and 1 run of 24" sewer pipe, existing MH beside MH #4 to existing MH beside #3, and about 4 more joints of pipe. Wellpoint pump and points turned today. Picked up.
Began demo/sawage of 24" sanitary sewer system. Removed two manholes and approximately 200' of pipe. Back-filled ditch back to grade. Dismantled remaining wellpoints, loaded and returned. Loaded all 24" pipe removed today and hauled away the clearing debris.
Larry met with city for a progress report and remaining schedule. Met with contractors truck foreman to discuss when they could began excavation of pond.