Back fill and dry up from last nights flood. Pull wellpoints and take up bypass lines and pumps. Back fill around all MH.
Dismantled all of the wellpoint system except 40' until existing manhole is removed from under 20" force main. Thompson pump began dismantle of by-pass system and loaded everything for return. Hauled 8 barriers to Kissimmee yard. Completed mud work of last sanitary sewer ring and cover. Concrete contractor can't give us a definite time to complete valley gutter and sidewalk. Put up berms along ditch banks to keep rain off from flooding structures.
Beau came by jobsite for a few minutes. He said to have John bring trailer over and drop it tomrrow to begin loading sanitary manholes and pipe from demo. Called John to set it up and to bring a fuel tank from shop to empty both by-pass pump tanks.
Problems: 2 more rain last night. Spent several hours pumping water again and cleaning up mud.