August 19, 2013

came in at 6:30, found job flooded. Water around MHs and had to pump out and dry up to raise MH ring and covers. Raised all 3 but not finished. Rained around noon another 2". Dried up and then came back again at 3:10. Knocked off at 3:30. i started to pump water till 5:30. Density man came and got compaction test around MH #4. Ok and MH #1 & 2 ok.

 

pumped out water from overnight rain. Added drier material and set sanitary manholes #2,3,4 to grade. pumped out overflow structure #108 into existing pond to avoid any turbid water from getting into lake. density tests on final backfill at manhole's #1 and #4 all passed. returned air hammer and compressor back to neff rental.

Called Thompson pumps to dismantle the by-pass system but they can't get there until tomorrow. Left wellpoint system in place to help dry up rains from last night. Beau called to check on progress and I told him about the rain and what we were doing about it. I told him we would need that trailer brought out to put demoed structures and pipe on for Kissimmee yard. 

Rained out at 3:30. 3" of rain overnight.