August 13, 2013

Paint inverts in sewer MHs. Get set up to lay storm. Set box and 90' of 15" ADS pipe. Compacted and backfill. Density man came and checked sewer ROWs. All passed.


Laid 15" HOPE from existing 15" RCP to bottom of pond slope. Set storm structure 108, mudded pipes, backfilled and compacted. Density tests taken on sanitary sewer all passed. Put in two lifts of backfill and compacted. Moved everything from area for sewer by pass installation tomorrow.

called Thompson pump to confirm set up of sewer by-pass tomorrow. Met with Toho inspector and notified required contacts that by-pass will be connected Thursday morning. Called Carl;'c concrete to set up core of existing manhole #1 for 10. Confirmed boot size, core size and depth of core. Joint of 24" sanitary sewer was delivered today along with 5 gallons of anti-hydro for core repair. Told Larry that Jess has copies of my daily reports he needs for city. Density tests scheduled for 9 am did not show up until 3:30.

Problems: concrete contractor did not show up again today. He is to re-schedule for tomorrow.