Backfill sewer lines and around MH (dug up around water MH to get up above water.) cement around pipes and build inverts
Cleaned out sanitary sewer manholes #2 and #3. Mudded pipes and modified inverts. Set MH riggers on #2 and #3. Sealed joints inside and out. Continued backfill and compaction process between #2 and #1.
called Beau to get by-pass quote from Thompson approved. he said to have Amy sign it and return. Picked up sewer boot for core of existing MH $1 Thursday. Told Larry we would only need one joint of 24" sewer to complete pipe. Also ordered epoxy paint for manholes and anti-hydro for sealing boots. Contractor couldn't get concrete until 3, so re-scheduled for 10 tomorrow. Still don't have the new proctor from test lab for backfill between #2 and #3. It was picked up a week ago, city inspector did not schedule any density tests for today.
Problems: Lab technician did not take density tests. City inspector did not schedule. No concrete until 10 tomorrow .