September 5, 2013

Cleaned all trees on the north end of job. All trees down and 75% cut up. Hauled off all 36" RCP. Met with wellpoint men. Saw cut for box culvert.


Began removing cypress trees for saw mill and stacking debris to haul off. Roll off broke down, grapple is down and dump site is too wet. Hauled all demo 36" RCP to Kissimmee yard. Cut cypress to 25' lengths until both chain saws went down. Saw cut asphalt for installation of box culvert. Loader went down with blown tire. 58 loads/ 1044 CY pond excavation.

met with Larry about wellpoints at box ulvert location and with wellpoint contractor to schedule installation of system. Made appointment with crane operator to meet tomorrow for clearing area above box culvert location. Called Beau about saws, loader, roll off and grapple. Also about alternating dumpsite for clearing debris. He is to call me back.