Started forms. Trash all little pipes in civic center dumpster. Started grading pond. I went and made skimmer for drain box (box culvert) skimmer . Had 2 brackets bent at tri city welders.
Stripped forms from inverts poured Friday for structure #s-100 and disposed of materials. Began removing excess fill from south end of pond top and pulling slopes. Completed fabrication of skimmer for structure #s-100 for installation tomorrow. Continued excavation on north end of pond and grading slopes. Talked to Larry about pond contractor and his lack of progress. I told him we will have to pump south end down to make repairs of slopes that are not correct. Scheduled partial layout for Wednesday with surveyor. And called Beau to discuss situation with pond contractor and his lack of acceptable progress.
Problems: need trucks haul spoil piles from pond area. Fill site for pond material is still too wet for import.