October 2, 2013

Set top on control box culvert box. Loaded out wellpoint pump and points. Had to put water in loader bucket and wet haul road because of dust. Hauled 18 loads of cross-ties wood and trash in top soil to Kissimmee yard to be screened.


Cleaned top wall of structure #s-100, installed double row of ramneck sealer and set to slab with rings and covers. Re-conected existing 4" underdrain to #s-100 and id a partial back-fill around structure with rock. Began hauling the contaminated/unsuitable material from pond to Kissimmee yard for screening later. 

Larry was on site this morning for setting of top slab on structure #s-100. We all took photos of process, including Butch from the city. Surveyors will not be here until friday to replace pond layout.