Pumped down pond, backfilled and compacted around control structure. Final density tests around structure and access dry all passed. Completed pot holes information of 20" force main and 14" water main. Installed 154' of 12" RCP north of Toho drive.
Toho water finally removed 2" irrigation service so we can install storm structure and pipe. They had four people trying to locate force main. Their information showed it is one location and 14'. We found it at 5' deep where they had locates for the water main. Gave drawing with elevations to Larry for 12" ADS. Plans call for 12" PVC but the existing pipe is ADS/HDPE.
Problems: Toho water's locate of 20" force main was 50' from actual location and had us looking for 5 hours.