Put down limerock for subgrade. Compacted, graded, and density taken. Put asphalt in open cut and side walk at seawall. Rolled all asphalt and sanded. All asphalt is temporary to open road. Removed all MOT required for open cut and opened to traffic. Clean up ROWs, set barriers at pipe end and barricades on ROW. Density tests on limerock base were 100+
Jimmy sent photos to Beau of the work zone upon completion. Took inventory of MOT for return monday. Took all equipment not needed back to yard. Took inventory of all stored materials with city inspector for draw requests.
Finished back filling and put down limerock. Got density and graded off t o pave. Tacked and paced. Clean up. Place road barriers in closed sidewalk and opened road. No rain (what happened!?)