August 8, 2013

Pre-tested all 24" sanitary sewer lines with all passing. No backfill or compaction because testing lab didn't come. Cut down large oak limbs over path of 48" AOS storm pipe. Set out MOT but did not close lane because concrete plant cancelled due to emergency pour.

called Thompson pump to set up delivery of sanitary sewer bypass for monday. Scheduled lamp and air test with Toho inspector tomorrow. Called Larry to tell him we need two joints of 24" sanitary to complete tie- ins.

Problems: density/lab technician did not show up. Concrete was bumped by plant and can't get it until tomorrow at 1.


Got all test equipment to test sewer pipe. Inspector wants us to pre-test pipe to ensure pipe test will pass. We had some problems but got all pretest off. Will set up for test in AM. Concrete boys could not get concrete today to pour curb sidewalk set up for tomorrow.