Removed asphalt and base at box culvert location. Set up required MOT fro road closure. Cleared overhead limbs for crane access at box culvert and set up pump for bypass system. Hauled one load of clearing debris from jobsite. Subcontractor continued pond excavation. 135 loads/2430 CY.
Contacted concrete sawing contractor and scheduled cutting of box culvert for Wednesday 8am. Dewatering contractor came to site and confirmed wellpoint installation for tomorrow am. Contacted concrete contractor to schedule forming and pouring collars for box culvert connection Thursday.