Completed demo of 24" RCP and 14x23 ERCP. Set 24" MES but couldn't get concrete to pour DOT collar as required. Hauled away last load of 24" sanitary sewer pipe. Did not lay any 14x23 ERCP due to water and muck that had to be removed first. Back-filled area, cleaned up for pipe with fill so it can be laid tomorrow. Set up 6" pump from shop to begin lowering water table in existing pond. need dumpster for concrete debris (sidewalk/MES)
Received an email stating that an arrangement had been made with the city to get concrete when we needed it. Contacted the person to have some delivered today, but he was not aware of the arrangement. I called Larry to confirm and was told everything was in place but still couldn't get any today. Jess called and may have worked it out so we can get it tomorrow. Beau said if we had to combine sidewalk, valley gutter and concrete collars to satisfy the load limit requirement, then to do so.
Received an email stating that an arrangement had been made with the city to get concrete when we needed it. Contacted the person to have some delivered today, but he was not aware of the arrangement. I called Larry to confirm and was told everything was in place but still couldn't get any today. Jess called and may have worked it out so we can get it tomorrow. Beau said if we had to combine sidewalk, valley gutter and concrete collars to satisfy the load limit requirement, then to do so.