October 4, 2013

Leigh Elliott

30 pallets. Loaded barges, barges moved for weekend. Moved boats at marina for weekend. Took Ben home.

Johnny Cullen

30 pallets. 66' have 40' till end also have 19 pallets left, should be able to stretch it. May have to get one more. Still need to install filter fabric on the 375'.

 

October 3, 2013

Leigh Elliott

25 pallets. Load barges and move barges. Heber worked with me. Last two trucks coming tomorrow.

Johnny Cullen

25 pallets. 55'. Rain and lightning ran us off.

 

October 2, 2103

Leigh Elliott

29 pallets. Move barges, loaded barges. 4 more truck due tomorrow. 2 friday.

Johnny Cullen

29 pallets. 63'. 225' of 325'. Used wheel instead of tape, came out 10' ahead. Will check tomorrow, was raining at end of day, also a lot of light bags.

 

September 30, 2013

Leigh Elliott

28 pallets. Walmart run. 9 total people. Heber went home at 12. Thomas left at 4. Load barges, move barges. Moved bag while waiting for empty barge.

Johnny Cullen

Finished filter fabric in section A 28 pallets. 60' in section B 40 pallets used so far.

 

September 27, 2013

Leigh Elliott

24 pallets. Load and move barges. Beau said 5 more truck loads to finish. Heber working with me. Alex quit? New guy Brady-driving van. Went by Gulf Harbour- moved a few boards- reset the cones. Looks fine.

Johnny Cullen

24 pallets. 50'. Started section B have about 25' done. Printed out termination notices and time sheets. Will commence with filter fabric as we have been. Have 20' left in section A.

 

September 26, 2013

Leigh Elliott

34 Pallets. Load barges, move barges. Move bat at marina. Heber was with me today.

Johnny Cullen

34 pallets. 73'. 15' left till end.